Trout Creek Recreation Center Parking Lot Asphalt Replacement
Association News, Capital Projects, Member News, Trout Creek Recreation CenterNov 18
WHAT IS THIS PROJECT?
- The Trout Creek Recreation Center parking lot asphalt and curbs will be replaced starting September 3, 2021 through mid-October.
WHY THIS PROJECT?
- The parking lot is in need of an upgrade to enhance membership and guest use.
WHAT ARE THE IMPACTS?
- Construction will occur from September 3 through mid-October 2021. Timeline includes:
- September 3-11: Set offset stakes, sawcut in front of new curb, curb demo and prep for new concrete
- Southeast side of the property curb and far east side parking by Northwoods (this will not hinder ingress and egress)
- Complete prep work by September 11
- September 27 – October 6: Concrete form pour and finish with machine
- Week of Oct. 4: Pulverize all remaining pavement, fine grade & prep for new paving
- Week of Oct. 11: Pave and stripe all pavement markings
- September 3-11: Set offset stakes, sawcut in front of new curb, curb demo and prep for new concrete
WHAT IS THE TIMELINE?
- This project should be complete by mid-October 2021.
WHAT IS THE TOTAL COST?
- The total cost is anticipated to be $411,000.