Detailed Asphalt Schedule May 6 - 10

2012 Asphalt Improvements

The annual parking area sweeping and striping is scheduled for May 6 – 10 at the Northwoods Clubhouse, Trout Creek Recreation Center and The Lodge Restaurant & Pub and Golf Course parking lots.

The scheduled parking lot area maintenance work will be performed in phases to accommodate parking availability in each parking lot; however, initial parking will be limited due to the maintenance work. Directional cones will direct traffic towards access and egress routes and towards available parking. Corridors will be marked and available to provide access to sidewalks and entryways. Asphalt maintenance work will be completed as quickly as possible with additional parking opening throughout each day.

Detailed Schedule of 2012 Asphalt Improvements:

Sunday, May 6
Northwoods Clubhouse and Trout Creek Recreation Center

Evening: set-up cones to direct traffic and parking to center parking spaces at Northwoods and set–up cones in 1/3 of Trout Creek parking area.

Monday, May 7
Northwoods Clubhouse and Trout Creek Recreation Center

7 a.m. – Northwoods Clubhouse: sweep and clean parking area of pebbles and debris

7:30 a.m. – 12 p.m. – Northwoods Clubhouse: begin striping on handicapped and outer perimeter parking spaces

1 – 4 p.m. – Trout Creek Recreation Center: sweep and clean parking area. Striping.

Tuesday, May 8
Northwoods Clubhouse and Trout Creek Recreation Center

6:30 a.m. – Northwoods Clubhouse: re-set directional cones to direct toward perimeter parking spaces and access/egress routes at Clubhouse.  Re-set to adjacent 1/3 of Trout Creek parking.

7 – 11 a.m. – Northwoods Clubhouse: sweep and clean center parking spaces and stripe.

12 – 4 p.m. – Trout Creek Recreation Center: sweep and clean parking coned area and stripe.

Wednesday, May 9
Trout Creek Recreation Center and The Lodge Restaurant & Pub

6:30 a.m. – Trout Creek Recreation Center: re-set cones and signage to adjacent 1/3 of Trout Creek parking. Set directional cones at The Lodge.

7 a.m. – Trout Creek Recreation Center: sweep and stripe final 1/3 of Trout Creek Parking

1 – 4 p.m. – The Lodge Restaurant & Pub: sweep and stripe Lodge and Golf parking 50 percent

Thursday, May 10
The Lodge Restaurant & Pub

6:30 a.m. – The Lodge: re-set to adjacent 50 percent of parking area

7 a.m. – Completion: sweep and stripe reaming parking area

We appreciate your patience and apologize for any inconvenience.

Post Tags

May 2, 2012

Post Categories

2014 Defensible Space Program

Get an early start on work that needs to be completed. Properties in Unit 2 (Lots 1-287) and Unit 8 (Lots 98-608) were...

Read More

Are You Fire-Safe?

Fire danger high this summer

Read More

Tahoe Donner Giving Fund Looking for Volunteers

You can help by joining our committee

Read More

No Open Fires

Dangerous Fire Conditions Expected

Read More