Tennis + Pickleball Court Improvements
Last updated on Aug. 3, 2026
WHAT IS THE PROJECT?
The project goal is to improve the experience for all users of the Tennis + Pickleball Center by providing dedicated regulation courts for both activities that address changing uses and safety concerns. The project also considers future impacts to the facility as the greater Tennis + Pickleball Center redevelopment project scope is created over the next few years.
The project will be phased over several years:
- Phase I:
- Reconstruct courts 7-9 with post-tension slab and convert to ten dedicated pickleball courts
- Reconstruct pickleball courts 9-10 with post-tension slab
- New 10′ sound attenuating PickleGlass wall, nets, and court separation fencing for the new pickleball area
- New permanent shade structures
- Resurface and restripe hybrid courts 10-11 to return to dedicated tennis courts
- Phase II – Reconstruct tennis courts 4-6 with post-tension slab, resurface and restripe
- Phase III – Reconstruct tennis courts 1-3 with post-tension slab, resurface and restripe
WHY THIS PROJECT?
Based on member feedback from multiple outlets over the last couple of years, staff has recognized a need to:
- Provide an improved pickleball experience and increase the number of dedicated courts;
- Make all tennis and pickleball courts regulation size (safety) and dedicated play without any hybrid striping; and,
- Separate disciplines for a more enjoyable playing experience for all.
WHAT ARE THE IMPACTS?
- Construction will impact a number of tennis and pickleball courts available for play for the remainder of the 2026 season:
- Pickleball courts 9-10 and Tennis courts 7-9 will be closed for the duration of the project
- Additional closures will be noticed as needed based on construction activities
- Temporary court closures may impact lessons, programs and court reservations due to reduced court capacity:
- 90-minute reservation limits; 30-minute extensions possible if availability allows
- Early registration recommended for lessons and programs
- Reconfiguration of courts resulting in 12 dedicated pickleball courts and 8 dedicated tennis courts.
WHAT IS THE PROJECT STATUS?
- Phase I design plans and permitting are complete.
- The board approved Phase I construction at the May 11, 2026, board meeting.
- Construction has commenced and is anticipated to continue into December 2026.
WHAT IS THE TOTAL COST OR BUDGET?
-
The Board of Directors has approved $1,835,872 for Phase I, utilizing 2026 New Capital Projects Funds and Repair and Replacement Fund. See the May 11, 2026, board meeting staff report for additional details.
DOCUMENTS
-
- July 31, 2026, board meeting presentation
- May 11, 2026, board meeting staff report
- May 11, 2026, board meeting presentation
- February 27, 2026, board meeting presentation
- December 19, 2025, board meeting presentation
- September 26, 2025, board meeting presentation
- August 26, 2025 Town Hall recording
- August 26, 2025 Town Hall presentation (PDF)
- June 27, 2025, board meeting presentation
HOW DO I PROVIDE FEEDBACK?
PLEASE NOTE: The Tennis + Pickleball Court Improvements project is in development by Tahoe Donner Association. The information provided is preliminary and subject to change. Drawings and renderings herein are for conveying Tahoe Donner Association’s vision of future projects. No warranties, expressed or implied, are made.