Pedestrian Bridge on the 18th Fairway
WHAT IS THE PROJECT?
- A new pedestrian bridge will be constructed on the golf course’s Trout Creek crossing on the 18th fairway.
WHY THIS PROJECT?
- The existing bridge has failed, and a full replacement is necessary.
WHAT ARE THE IMPACTS?
- Construction is scheduled for late-September to mid-October 2026.
- Temporary impacts to the #18 fairway are anticipated during construction, and play on the fairway will need to be altered during construction.
WHAT IS THE STATUS?
- Project design is complete.
- Permits have been issued from all required agencies.
- The board approved construction at the July 31, 2026, board meeting.
- Staff is contracting for construction.
WHAT IS THE TOTAL COST OR BUDGET?
- $25,000 in 2022 for professional services
- $49,500 in 2024 for professional services
- $108,388 in 2026 for construction
HOW DO I PROVIDE FEEDBACK?
DOCUMENTS
- July 31, 2026, board meeting presentation
- September 26, 2025, board meeting presentation
- Nov. 22, 2024 board meeting presentation
- July 26, 2024 board meeting presentation
- Jan. 26, 2024 board meeting presentation
- July 28, 2023 board meeting presentation
- Jan. 27, 2023 board meeting presentation
PLEASE NOTE: The Pedestrian Bridge on the 18th Fairway project is in development by Tahoe Donner Association. The information provided is preliminary and subject to change. Drawings and renderings herein are for conveying Tahoe Donner Association’s vision of future projects. No warranties, expressed or implied, are made.