Last updated on May 8, 2026

WHAT IS THE PROJECT?

The project goal is to improve the experience for all users of the Tennis + Pickleball Center by providing dedicated regulation courts for both activities that address changing uses and safety concerns. The project also considers future impacts to the facility as the greater Tennis + Pickleball Center redevelopment project scope is created over the next few years.

The project will be phased over several years:

  • Phase I:
    • Reconstruct courts 7-9 with post-tension slab and convert to ten dedicated pickleball courts
    • Reconstruct pickleball courts 9-10 with post-tension slab
    • New 10′ sound attenuating PickleGlass wall, nets, and court separation fencing for the new pickleball area
    • New permanent shade structures
    • Resurface and restripe hybrid courts 10-11 to return to dedicated tennis courts
  • Phase II – Reconstruct tennis courts 4-6 with post-tension slab, resurface and restripe
  • Phase III – Reconstruct tennis courts 1-3 with post-tension slab, resurface and restripe

WHY THIS PROJECT?

Based on member feedback from multiple outlets over the last couple of years, staff has recognized a need to:

  • Provide an improved pickleball experience and increase the number of dedicated courts;
  • Make all tennis and pickleball courts regulation size (safety) and dedicated play without any hybrid striping; and,
  • Separate disciplines for a more enjoyable playing experience for all.

WHAT ARE THE IMPACTS?

  • Construction will impact the number of tennis and pickleball courts available for play during portions of the 2026 season (see May 11, 2026 Special Board Meeting Presentation).
  • Reconfiguration of courts resulting in 12 dedicated pickleball courts and 8 dedicated tennis courts.

WHAT IS THE PROJECT STATUS?

  • Phase I design plans are complete.
  • The board approved Phase I construction at the May 11, 2026, board meeting.
  • Staff is working through some final permitting items with the Town of Truckee and will provide an updated construction schedule once we have more information. Construction will commence as soon as all permitting is complete.

WHAT IS THE TOTAL COST OR BUDGET?

  • The Board of Directors has approved $1,835,872 for Phase I, utilizing 2026 New Capital Projects Funds and Repair and Replacement Fund. See the May 11, 2026, board meeting staff report for additional details.


DOCUMENTS


HOW DO I PROVIDE FEEDBACK?



PLEASE NOTE: The Pickleball Courts Enhancement project is in development by Tahoe Donner Association. The information provided is preliminary and subject to change. Drawings and renderings herein are for conveying Tahoe Donner Association’s vision of future projects. No warranties, expressed or implied, are made.