Trout Creek Recreation Center Parking Lot Asphalt Replacement

WHAT IS THE PROJECT?

  • The Trout Creek Recreation Center parking lot asphalt and curbs have been replaced. The project is complete.

WHY THIS PROJECT?

  • The parking lot asphalt and curbs have exceeded their useful life. This is a scheduled replacement reserve project to keep our facilities in a well-maintained condition.

WHAT ARE THE IMPACTS?

  • Construction occured from September 3 through mid-October 2021. Impacts varied depending on the construction activity. All efforts were made to keep the Rec Center facility open during this time.

WHAT IS THE TIMELINE?

  • Timeline includes:
    • September 3-11: Set offset stakes, sawcut in front of new curb, curb demo and prep for new concrete
      • Southeast side of the property curb and far east side parking by Northwoods (this will not hinder ingress and egress)
      • Complete prep work by September 11
    • September 27 – October 6: Concrete form pour and finish with machine
    • Week of October 4: Pulverize all remaining pavement fine grade and prep for new paving
    • Week of October 11: Pave and stripe all pavement markings
    • Project complete in mid-October

WHAT IS THE TOTAL COST?

  • The total cost was anticipated to be $411,000.

HOW DO I PROVIDE FEEDBACK?


DOCUMENTS