Scope: By adding a new parking lot at the downhill ski area, Tahoe Donner now offers an additional 65 parking stalls available for guest use which is a 33% increase in parking capacity. We now have a total capacity of 260 vehicles spaces on-site, an additional shuttle stop, and on-street overflow parking available during peak season. This enables us to offer our guests additional convenience and services throughout the ski season.

Schedule:

  • August 2011; Application Filed with Town of Truckee and Planning
  • November 2011; Planning Commission approvals
  • Construction Permit received August 2012
  • Construction started September 10th
  • September 21st; Construction progress = 50%
  • October 4th; Construction and stall striping = 100%

Team: Capital Projects staff, Atlas Contractors, K.B. Foster Engineering