WHAT IS THE PROJECT? 

  • A member-led General Plan Committee (GPC) taskforce has worked since 2016 gathering member feedback and diligently planning to meet the needs of the community. The soft re-opening of the Trout Creek Recreation Center occurred on Saturday, February 8, including the new cardio room and weight room (Phase 2) located at the East end of the building.

WHY THIS PROJECT? 

  • Adapt the facility to changing member needs
  • Safety, comfort and member experience
  • Increase usable space

WHAT ARE THE IMPACTS? 

  • PHASE 1 – Pool Side: There will only be minor workout impacts, including temporary entrance at the west side of building.
  • PHASE 2 – Gym Side: Equipment and classes will be relocated to meet the fitness needs of as many members as possible.
  • From mid-October through January, fitness class impact will include a reduction in class frequency and variety. In order to best accommodate our members, some classes will be relocated to either Alder Creek Adventure Center or Northwoods Clubhouse.

: 


WHAT IS THE TIMELINE? 

  • In an attempt to complete this project as quickly as possible, construction crews will be working seven days per week from 7AM-7PM.
  • Construction began on January 7, 2019, on the two-phased renovation of the Trout Creek Recreation Center.
  • PHASE 1 – Pool Side: Starts Jan. 2019 and lasts approximately six months.
  • PHASE 2 – Gym Side: Starts mid-2019 and lasts approximately eight months.
    • PHASE 2aJuly – mid-October 2019
      • Fitness Classes: Unaffected
      • Weight + Cardio Rooms: All the equipment from the existing weight and cardio rooms will be distributed to multipurpose rooms B and C (see map below) and in a heated/ventilated tent that has been erected on the basketball court.

      Tent information:

      • Heated (when needed) and well-ventilated
      • 3,200 square feet
      • Powered by generator for lighting and minor equipment needs
      • Includes asphalt walkway

      PHASE 2bOctober – January 2020


WHAT IS THE COST?

  • $2.4 million estimated cost, which includes all hard and soft costs associated with this capital improvement.

HOW DO I PROVIDE FEEDBACK?


DOCUMENTS