Scope: In lieu of a brand new Maintenance Facility, the TDA Board of Directors supported a comprehensive remodel alternative, where construction commenced in November of 2012, and where the following improvements are now complete:

  • Forestry Building removal for additional parking stalls
  • New Vehicle Storage Building (2,400 SF)
  • Maintenance Building Remodel  (5,800 SF)
  • Vehicle Carport (1,500 SF)
  • Maintenance yard and drainage improvements

Schedule: 

  • August 2012; Plans submitted to Town of Truckee
  • September 10; Demo work and investigation process begins
  • October 30; Building Permits received
  • November 2012; Construction commences
  • April 2013; Mainteance Facilty remodel complete

Team: Peter Gerdin Architect, J&S Construction