WHAT IS THE PROJECT?

  • Re-paving of all cart paths. It involves tree and root removal, re-routing and widening paths as needed, complete pulverization and new asphalt paving throughout, except where paths were recently replaced.

WHY THIS PROJECT?

  • Cart paths necessitate replacement due to extensive root damage, bumps, cracking and general deterioration.
  • Cart path damage impacts a golf cart’s useful life; repairs will ultimately extend the life of the cart fleet.

WHAT ARE THE IMPACTS?

  • Over-the-snow tree removal operations are completed and clean-up is wrapping up in early May 2024.
  • Back nine replacement is anticipated in October 2024.
  • Please anticipate normal construction noise disturbance, including heavy machinery and equipment.
  • Portions of the golf course may be closed during paving demolition and new paving.

WHAT IS THE STATUS?

  • Front nine replacement is complete.
  • The project schedule for holes 10-18 will take approximately 30 working days and be completed in October 2024. Please note that this date could change if conditions improve or deteriorate due to weather.
  • Contractors plan to work from 7AM to 5PM Monday through Friday and from 8AM to 5PM on Saturdays.

WHAT IS THE TOTAL COST OR BUDGET?

  • The Board of Directors has approved $1,578,414 for construction, funded from the Replacement Reserve Fund.

DOCUMENTS


HOW DO I PROVIDE FEEDBACK?


PLEASE NOTE: The Golf Course Cart Path Renovation Project is in development by Tahoe Donner Association. The information provided is preliminary and subject to change. Drawings and renderings herein are for conveying Tahoe Donner Association’s vision of future projects. No warranties, expressed or implied, are made.