WHAT IS THE PROJECT?

  • The Beach Club Marina deck will be expanded into the underutilized lawn area. A landscape architect is creating a plan to allow for ADA compliance, shade structures, fire pit, an outdoor bar, windscreens and more.

WHY THIS PROJECT?

  • These updates will provide a larger area for the membership to dine while at the grill area. It will also serve as a place to shelter from the elements of those hot or windy summer afternoons or to just enjoy a cocktail by the lake in the evening.

WHAT ARE THE IMPACTS?

  • The deck area will be unavailable during construction. The project will not be constructed during the peak summer season from July 1 through Sept. 5.

WHAT IS THE TIMELINE?

  • Construction is slated for fall 2022 but is pending board approval, permit approval and contractor availability.

WHAT IS THE TOTAL COST?

  • The total cost is anticipated to be approximately $322,000.

HOW DO I PROVIDE FEEDBACK?


DOCUMENTS

Please note: All documents and meeting recordings can be found on the member portal.